Fujairah 2 is a flagship large scale cogeneration asset and one of the UAE’s most critical power and water infrastructure projects, underpinning energy and water security in the northern emirates.
Fujairah 2 – Fujairah Asia Power Company (FAPCO)
2,000 MW | 130 MIGD
CCGT + Desalination
Umm Al Nar B is a strategic gas‑fired cogeneration power and water plant supporting Abu Dhabi’s electricity and desalinated water supply under a long‑term Power and Water Purchase Agreement (PWPA). As a core asset within the emirate’s utility system, the plant plays a vital role in meeting baseload demand through reliable, large‑scale generation.
Umm Al Nar B – Arabian Project Co.
1,531.9 MW | 94.4 MIGD
CCGT + Desalination
Al Taweelah A1 is a gas fired cogeneration power and water plant delivering electricity and desalinated water to Abu Dhabi under a long term Power and Water Purchase Agreement (PWPA).
Al Taweelah A1 – Gulf Total Tractebel Power Company
1,590 MW | 84 MIGD
CCGT + Desalination
Mirfa 2 is a reverse osmosis (RO) water desalination plant that strengthens Abu Dhabi’s long term water security through large scale, efficient desalination capacity. The project supports the Emirate’s growing water needs by delivering a reliable and sustainable supply of potable water using advanced RO technology.
Mirfa 2 RO Water Desalination Company
120 MIGD
Desalination - RO
Mirfa International Power & Water Company (MIPCO) is a large‑scale gas‑fired cogeneration facility that plays a critical role in supporting Abu Dhabi’s power and water requirements. The project is designed around high‑efficiency combined‑cycle generation, enabling the simultaneous production of electricity and desalinated water from a single integrated system.
Mirfa – International Power & Water Company (MIPCO)
1,600 MW | 54 MIGD
CCGT + Desalination - RO
Shuweihat 2 is a large‑scale gas‑fired cogeneration power and water desalination plant located in Abu Dhabi, United Arab Emirates.
Shuweihat 2 – Ruwais Power Company
1,496 MW
CCGT
Shuweihat 1 is undergoing a major transformation from a legacy power‑and‑water cogeneration facility into a 1.1 GW natural gas‑fired open‑cycle power plant, designed to deliver flexible reserve capacity to Abu Dhabi’s electricity system. Originally commissioned in 2005, the plant has played a central role in the UAE’s energy infrastructure for nearly two decades.
Shuweihat 1 – Shuweihat CMS International Power Company (SCIPCO)
1.5 GW
OCGT
Barka IV is a large-scale seawater reverse osmosis desalination plant in Oman, supporting potable water supply through efficient, high-capacity desalination technology since 2018.
Barka 4 Desalination Company
61.8 MIGD
Reverse osmosis (RO)
Barka 3 is a gas fired combined cycle power plant designed to meet Oman’s growing electricity demand through reliable and efficient generation. Operating under long term contractual arrangements, the plant plays an important role in supporting national grid stability.
Barka 3 – Al Suwadi Power Company
736.5 MW
CCGT